Introduction

For this document, it is assumed that a minimum of two people are present at the firing:

  • The Firing Director (FD)
  • The Safety Officer (SO)

However, it is suggested that the following people be present as well:

  • The Operations Overseer (OO)
  • The Data Recorder (DR)

For more on the positions, see Responsibilities of the Rail Gun Team.

  1. Flip injector ARM switch on control box to allow EMRG to be fired
    • Flip injector ARM switch on control box to allow EMRG to be fired

  2. Begin countdown from 5, down to 1, followed by "FIRE". On FIRE, press FIRE button on control box.
    • Begin countdown from 5, down to 1, followed by "FIRE".

    • On FIRE, press FIRE button on control box.

    • After firing IMMEDIATELY end the camera's cycle to acquire footage of the firing

  3. Immediately after firing switch the resistor bank to ON and turn off firing switch
    • Immediately after firing switch the resistor bank to ON and turn off firing switch

  4. Do not remove the power supply to the control box until the manual discharge pin has been pulled.
    • Do not remove the power supply to the control box until the manual discharge pin has been pulled.

    • Allow four (4) minutes for capacitors to fully discharge.

  5. Pull pin for manual discharge release.
    • Pull pin for manual discharge release.

    • You may now disconnect the power to the control box.

    • Disconnect the 25-pin data collection cable.

    • Disconnect the 5-point control cable.

    • Disconnect the 2-point power cable.

  6. Turn Red Safety Light off
    • Turn Red Safety Light off

Finish Line

Collin MacGregor

Member since: 02/26/2012

1 Reputation

7 Guides authored

Team

CPPP Members Member of CPPP Members

1 Member

7 Guides authored

0 Comments

Add Comment

View Statistics:

Past 24 Hours: 0

Past 7 Days: 0

Past 30 Days: 1

All Time: 57